Excavation & Earthwork Calculator

Calculate the volume of soil to be dug for footings, trenches or a basement, plus truck loads and cost.

ConstructionInstant resultsFormula shown100% in your browser

Inputs

Formula

  • Excavated volume = L × W × D × quantity
  • Loose (bulked) volume = volume × bulking factor
  • Truck loads = loose volume ÷ tipper capacity

Digging is measured in the ground — length by width by depth. But soil swells once loosened, so the volume you have to cart away is 15–40% larger depending on the soil. Contractors quote per cubic metre of in-situ excavation, while truck hire depends on the loose volume.

Step-by-step calculation

  1. 1

    Volume

    L × W × D × qty

    3,000 cu ft

  2. 2

    In m³

    × 0.0283

    84.95 m³

  3. 3

    Loose volume

    × 1.25 bulking

    106.19 m³

Worked example

  1. 1A 30 × 20 × 5 ft basement = 3,000 cu ft = 84.95 m³.
  2. 2Normal soil bulks 25% → 106.2 m³ of loose spoil.
  3. 3At 8 m³ per tipper that is 14 trips; at ₹250/m³ the digging costs ₹21,240.

Tips

  • Keep a part of the soil on site for back-filling — you usually need 30% of it back.
  • Slope or shore any pit deeper than 1.5 m; collapsing trenches are the most common site accident.

Frequently asked questions

How many cubic feet in a cubic metre?

35.31 cu ft. So 100 cu ft is 2.83 m³.

Why is the removed volume larger than the pit?

Loose soil occupies more space than packed soil — this is called bulking and is typically 25%.

What does excavation cost?

Machine excavation runs ₹150–₹350 per m³ in normal soil; rock breaking costs several times more.